State of the project on 30.04.2024. year

State of the project on 30.04.2024. year

During the month of April, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

 

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of April, preparatory and earthworks for the mechanical facility were carried out pretreatment and biological treatment of waste water, works on the administrative building of the Plant and preparatory works on the fields for earthing of sludge, preparatory works on covered buildings parking for cars and covered parking for trucks and special vehicles.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Picture of the construction site

  • Picture 2: Inlet pumping station of the mechanical pretreatment facility

  • Picture 3 and 4: Biological waste water treatment facility

State of the project on 31.03.2024. year

State of the project on 31.03.2024. year

During the month of March, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of March, preparatory and earthworks for the mechanical building were carried out pre-treatment and biological treatment of waste water, construction of foundations for the Plant fence, works on administrative building of the Plant and preparatory works on the fields for earthing of sludge.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Picture of the construction site

  • Picture 2: Inlet pumping station of the mechanical pretreatment facility

  • Picture 3: Biological wastewater treatment facility

State of the project on 29.02.2024. year

State of the project on 31.01.2024. year

During the month of February, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of February, preparatory and earthworks for the facility of mechanical pretreatment and biological treatment of waste water, construction of a piezometer, construction of the foundations of the Plant’s fences, and work on the Plant’s administrative building were carried out.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Picture of the construction site

  • Picture 2: Concreting of the fence

  • Picture 3: Administrative building – concreting of AB slab

  • Picture 4: Performance of the piezometer

State of the project on 31.01.2024. year

State of the project on 31.01.2024. year

During the month of January, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the months of November and December, preparatory and earthworks were carried out on the access road and preparatory and earthworks on the excavation for the facility of mechanical pretreatment and biological treatment of waste water.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Preparation of reinforcement baskets for the foundation of the fence
  • Picture 2 and 3: Concreting the foundation of the fence
  • Picture 4: Concreting of the water measuring shaft

State of the project on 31.12.2023. year

State of the project on 31.12.2023. year

During the month of Decmber, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

Realization of works from 31.12.2023. years below  

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

  • As part of the works on Group 1, 18,965.46 m of drainage pipelines and 11,242.87 m of water supply pipelines were constructed in the settlements of Semeljci, Kešinci and Koritna.

GROUP 2 – VRBICA SETTLEMENT

  • As part of the works on Group 2, 18,965.46 m of drainage pipelines were constructed in the settlements of Mrzović and Vrbica.

GROUP 3

  • As part of the works on Group 3 in the area of ​​the city of Đakovo, 12,197.80 m of water supply pipelines were constructed.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the months of November and December, preparatory and earthworks were carried out on the access road and preparatory and earthworks on the excavation for the facility of mechanical pretreatment and biological treatment of waste water.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Pictures: Earthworks on the excavation of a construction pit for mechanical pretreatment and biological treatment of water

Pictures: Earthworks on the access road

State of the project on 30.11.2023. year

State of the project on 30.11.2023. year

During the month of Decmber, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

Realization of works from 30.11.2023. year below  

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

  • As part of the works on Group 1, 18,965.46 m of drainage pipelines and 11,242.87 m of water supply pipelines were constructed in the settlements of Semeljci, Kešinci and Koritna.

GROUP 2 – VRBICA SETTLEMENT

  • As part of the works on Group 2, 18,965.46 m of drainage pipelines were constructed in the settlements of Mrzović and Vrbica.

GROUP 3

  • As part of the works on Group 3 in the area of ​​the city of Đakovo, 12,197.80 m of water supply pipelines were constructed.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of November, preparatory and earthworks were carried out on the access road and preparatory and earthworks on the excavation for the facility of mechanical pretreatment and biological treatment of waste water.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Pictures: Earthworks on the excavation of a construction pit for mechanical pretreatment and biological treatment of water

Pictures: Earthworks on the access road

Visit to the Project construction site

VISIT TO THE CONSTRUCTION SITE of the project – “Project to improve the water utility infrastructure of the Semeljci agglomeration”

________________________________________________________________________________________________

RADIO REPORTAGE 1

RADIO REPORTAGE 2

TV REPORTAGE

In the premises of the Municipality of Semeljci on November 8, 2023. In 2008, the coordination and visit to the construction site of the EU project “Project to improve the water utility infrastructure of the Semeljci agglomeration” was held, co-financed from the Cohesion Fund.

The press conference was attended by Mr. Davor Vukmirić, Deputy General Director of Hrvatske Voda, Mr. Ivan Kočiš, Director of Đakovočko vodovod d.o.o., Mr. Grga Lončarević, Head of Semeljci Municipality, and other project partners.

CURRENT STATE OF WORK ON THE PROJECT

Total estimated value of the Project:

219.567.261,25 kn – 29.141.583,54  € (total amount of the Project)

175.653.809,00 kn  – 23.313.266,83 € (eligible costs)

121.734.196,10 kn –  16.156.904,39 €  (EU resources)

Contracted for now:

18,266,478.38 € (Part of the components remaining to be contracted as part of the procurement of communal equipment for the maintenance of drainage and water supply systems).

As part of the Project, there are three contracts for the construction of line buildings (construction of water supply and drainage pipelines) and a contract for the construction of a wastewater treatment plant with a capacity of 4,800 ES.

In total, the Project envisages the construction of 50,826 m of drainage pipelines and the reconstruction and construction of 23,540 m of water supply pipelines with accompanying facilities (manholes, pumping stations, valve shafts, pressure boosting stations).

Building permits have been obtained for linear buildings, construction contracts have been signed and the works are in the final stages of execution. A Building Permit has been obtained for the Wastewater Treatment Plant, and the work on the ground is expected to begin by the end of the month.

BRIEF OVERVIEW OF WORKS

LINE BUILDINGS

Group of works 1

  • includes works on the construction of the drainage system in the villages of Semeljci, Kešinci and Koritna, as well as the reconstruction and construction of water supply pipelines in the area of ​​the municipalities of Viškovci and Semeljci.

  • The construction of 31,860 m of drainage pipelines and 11,243 m of water supply pipelines is planned.

  • This contract also provides for the construction of home connections to the water supply system, the preparation of home connections to the drainage system, and the replacement of existing water meters with new ones.

  • The value of the contracted works is approximately EUR 7 million (€6,937,599.62).

  • The contractor started the work in August 2021, and the expected completion date is February 2024.

  • The water supply and drainage pipelines envisaged by the project have been fully implemented.

  • At the moment, preparations are being made for house connections and final landscaping works – rehabilitation of driveways and public areas.

  • As part of the contract, 31,875.70 m of drainage pipelines and 11,242.87 m of water supply pipelines were constructed.

Group of works 2

  • includes works on the construction of the drainage system in the settlements of Vrbica and Mrzović. For the Mrzović settlement, the works have been brought to an end and the Operating Permit was issued in June 2023. The project envisages the construction of a total of 18,965 m of drainage pipeline. The value of the contracted works is almost EUR 3 million (€2,897,660.90). The contractor started the work in August 2021, and the completion of the work and the issuance of the Operating Permit is expected at the beginning of 2024. In the village of Vrbica, the drainage pipelines have been completely installed, and preparations are currently being made for house connections and finishing works on landscaping – rehabilitation of driveways and public areas. As part of the contract, 18,995.06 m of drainage pipelines were constructed.

Group of works 3

  • includes works on the construction of a bypass pipeline around the town of Đakovo and works on improving the system of the wider Đakovo area. The contracted value of the works is €1,623,675.69. The contractor started the work in August 2021, and the use permit was obtained in April of this year. As part of the contract, 12,297.53 m of pipelines were built.

 

WASTEWATER PURIFICATION DEVICE

The location of the wastewater treatment plant is in the village of Semeljci. As part of this component, an access road and a wastewater treatment plant will be built. A Building Permit was obtained for the access road, and earthworks and works on filling and compacting the lower load-bearing layers of the pavement structure were carried out.

For the construction of a waste water treatment plant, the main project was drawn up and a building permit was obtained. Confirmation of the validity of the construction permit is expected by the end of November.

  • contracted value €270,435.20
  • the start date is June 1, 2022, and the planned completion date is May 2025.

_________________________________________________________________________________________________

As part of the Project, the Procurement of communal equipment for the maintenance of drainage and water supply systems is planned: combined vehicle with recycling, measuring vehicle, combined excavator, backhoe, work vehicles for transporting materials and workers, measuring equipment, work equipment and IT equipment with an estimated value of 981,153.36 €.

So far, the following have been delivered: Combined excavator, backhoe, two vehicles for transporting materials and workers, and measuring equipment. The total value of the delivered equipment is €402,855.94.

The execution of the works was preceded by the activities of resolving property legal relations. Agreements were concluded on the establishment of easement rights on 359 parcels.

In addition to the above, the Project also includes the services of Supervision, Publicity and visibility, and Project Management.

The project to improve the water utility infrastructure of the Semeljci agglomeration was approved within the Operational Program “Competitiveness and Cohesion” 2014-2020. (OPKK 14 – 20), but will be redistributed to the National Recovery and Resilience Program (NRRP) and funding will continue through NPRO funds.

During August 2023, the User submitted the project application documentation for financing through the National Recovery and Resilience Plan 2021 – 2026 to the competent authorities.

 

State of the project on 31.10.2023. year

State of the project on 31.10.2023. year

During the month of October, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total,50.620,02 meters of drainage pipelines (99,59%) have been constructed so far, out of a total of 50,826.46 meters and 23,440.67 meters of water supply pipelines (99.82%), out of a total of 23,482.87 meters planned.

Realization of works from 31.10.2023. year below  

So far, the works have included the following streets:

  • Semeljci –  Street Braće Radića,  Street Tune Rakitića,  Street Kralja Tomislava, Kolodvorska  Street,  Street Antuna Mihanovića,  Street Vladimira Nazora, Školska  Street,  Street Augusta Šenoe, Street Ivana Kozarca                                                      
  • Koritna –  Street Josipa Kozarca,  Street Marka Mutaje,  Street Rade Končar, Strossmayer Street, Street Matije Gupca, Street Kolodvorska, Street Braće Radića

  • Kešinci –  Street Ive Lole Ribara,  Street Matije Gupca,  Street Solara,  Street Ljudevita Gaja,  Street Braće Radić, Doljanska, Balkanska

  • Vrbica –  Street Kešinačka,  Street Mikanovačka, Street Đurđanačka, Street Mrzovička

  • Mrzović –  Street Vrbička,  Street Bojana,  Street Crna Bara,  Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – VRBICA SETTLEMENT

 

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant. During the month of August, the Contractor continued with the construction of the access road. Project documentation for the waste water treatment plant is being prepared, and in the coming period, a request for a building permit for its construction will be submitted.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Pictures: Construction of DTK well D2

Pictures: Earthworks on the access road

State of the project on 30.09.2023. year

State of the project on 30.09.2023. year

During the month of September, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total,50.620,02 meters of drainage pipelines (99,59%) have been constructed so far, out of a total of 50,826.46 meters and 23,440.67 meters of water supply pipelines (99.82%), out of a total of 23,482.87 meters planned.

Realization of works from 30.09.2023. year below  

So far, the works have included the following streets:

  • Semeljci –  Street Braće Radića,  Street Tune Rakitića,  Street Kralja Tomislava, Kolodvorska  Street,  Street Antuna Mihanovića,  Street Vladimira Nazora, Školska  Street,  Street Augusta Šenoe, Street Ivana Kozarca                                                      
  • Koritna –  Street Josipa Kozarca,  Street Marka Mutaje,  Street Rade Končar, Strossmayer Street, Street Matije Gupca, Street Kolodvorska, Street Braće Radića

  • Kešinci –  Street Ive Lole Ribara,  Street Matije Gupca,  Street Solara,  Street Ljudevita Gaja,  Street Braće Radić, Doljanska, Balkanska

  • Vrbica –  Street Kešinačka,  Street Mikanovačka, Street Đurđanačka, Street Mrzovička

  • Mrzović –  Street Vrbička,  Street Bojana,  Street Crna Bara,  Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – VRBICA SETTLEMENT

 

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant. During the month of August, the Contractor continued with the construction of the access road. Project documentation for the waste water treatment plant is being prepared, and in the coming period, a request for a building permit for its construction will be submitted.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Pictures: Construction of DTK well D2

Pictures: Earthworks on the access road

State of the project on 31.08.2023. year

State of the project on 31.08.2023. year

During the month of August, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 49.614,21 meters of drainage pipelines (97,61%) have been constructed so far, out of a total of 50,826.46 meters and 23,436.71 meters of water supply pipelines (99.80%), out of a total of 23,482.87 meters planned.

Realization of works from 31.08.2023. year below  

So far, the works have included the following streets:

  • Semeljci –  Street Braće Radića,  Street Tune Rakitića,  Street Kralja Tomislava, Kolodvorska  Street,  Street Antuna Mihanovića,  Street Vladimira Nazora, Školska  Street,  Street Augusta Šenoe, Street Ivana Kozarca                                                      
  • Koritna –  Street Josipa Kozarca,  Street Marka Mutaje,  Street Rade Končar, Strossmayer Street, Street Matije Gupca, Street Kolodvorska, Street Braće Radića

  • Kešinci –  Street Ive Lole Ribara,  Street Matije Gupca,  Street Solara,  Street Ljudevita Gaja,  Street Braće Radić, Doljanska, Balkanska

  • Vrbica –  Street Kešinačka,  Street Mikanovačka, Street Đurđanačka, Street Mrzovička

  • Mrzović –  Street Vrbička,  Street Bojana,  Street Crna Bara,  Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – VRBICA SETTLEMENT

 

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant. During the month of August, the Contractor continued with the construction of the access road. Project documentation for the waste water treatment plant is being prepared, and in the coming period, a request for a building permit for its construction will be submitted.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Picture 1 and 2: Pressure test of the installed water supply pipeline

Picture 3 and 4: Backfilling of the trench of the water supply pipeline