State of the project on 31.10.2022. year

State of the project on 31.10.2022. year

During the month of October, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 34,307.11 meters of drainage pipelines (67.50%) have been constructed so far, out of a total of 50,826.46 meters and 16,579.80 meters of water supply pipelines (70.60%), out of a total of 23,482.87 meters planned.

  • The works are carried out smoothly and according to plan

State of the project on 30.09.2022. year

State of the project on 30.09.2022. year

During the month of September, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 27,546.27 meters of drainage pipelines (54.20%) have been constructed so far, out of a total of 50,826.46 meters and 14,492.80 meters of water supply pipelines (61.72%), out of a total of 23,482.87 meters planned.

Realization of works from 30.09.2022. years below

So far, the works have included the following streets:

  • Semeljci – Street Braće Radića, Street Tune Rakitića, Street Kralja Tomislava, Kolodvorska Street, Street Antuna Mihanovića, Street Vladimira Nazora, Školska Street

  • Koritna – Street Josipa Kozarca, Street Marka Mutaje, Street Rade Končar

  • Kešinci – Street Ive Lole Ribara, Street Matije Gupca, Street Solara, Street Ljudevita Gaja, Street Braće Radić, Doljanska, Balkanska

  • Vrbica – nisu se izvodili radovi 

  • MrzovićStreet Vrbička, Street Bojana, Street Crna Bara, Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

State of the project on 31.08.2022. year

State of the project on 31.08.2022. year

During the month of August, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

 

In total, 27,546.27 meters of drainage pipelines (54.20%) have been constructed so far, out of a total of 50,826.46 meters and 14,492.80 meters of water supply pipelines (61.72%), out of a total of 23,482.87 meters planned.

Realization of works from 31.08.2022. years below

So far, the works have included the following streets:

  • Semeljci – Street Braće Radića, Street Tune Rakitića, Street Kralja Tomislava, Kolodvorska Street, Street Antuna Mihanovića, Street Vladimira Nazora, Školska Street

  • Koritna – Street Josipa Kozarca, Street Marka Mutaje, Street Rade Končar

  • Kešinci – Street Ive Lole Ribara, Street Matije Gupca, Street Solara, Street Ljudevita Gaja, Street Braće Radić, Doljanska, Balkanska

  • Vrbica – nisu se izvodili radovi 

  • MrzovićStreet Vrbička, Street Bojana, Street Crna Bara, Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

State of the project on 31.07.2022. year

State of the project on 31.07.2022. year

During the month of July, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

A total of 23,946.75 meters of drainage pipelines (47.11%) have been constructed so far, out of a total of 50,826.46 meters, and 12,842.80 meters of water supply pipelines (54.69%), out of a total of 23,482.87 meters planned.

Realization of works from 31.07.2022. years below

So far, the works have included the following streets:

  • Semeljci – Street Braće Radića, Street Tune Rakitića, Street Kralja Tomislava, Kolodvorska Street, Street Antuna Mihanovića, Street Vladimira Nazora, Školska Street 

  • Koritna – Street Josipa Kozarca, Street Marka Mutaje, Street Rade Končar 

  • Kešinci – Street Ive Lole Ribara, Street Matije Gupca, Street Solara, Street Ljudevita Gaja, Street Braće Radić, Doljanska, Balkanska 

  • Vrbica – nisu se izvodili radovi 

  • Mrzović – Street Vrbička, Street Bojana, Street Crna Bara, Street Potok, ŽC 4132 

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

State of the project on 30.06.2022. year

State of the project on 30.06.2022. year

During the month of June, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

A total of 19,387.58 meters of drainage pipelines (38.14%), out of a total of 50,826.46 meters and 12,197.80 meters of water supply pipelines (51.94%), have been constructed so far, out of a total of 23,482.87 meters planned.

Realization of works from 30.06.2022. year below

So far, the works have included the following streets:

  • Semeljci – Braće Radića Street, Tune Rakitića Street, Kralja Tomislava Street, Kolodvorska Street, Antun Mihanovića Street, Vladimira Nazor Street, Školska Street

  • Koritna – Josipa Kozarac Street, Marko Mutaje Street, Rade Končar Street

  • Kešinci – Iva Lola Ribara Street, Matije Gupca Street, Solara Street, Ljudevita Gaja Street, Braće Radić Street, Doljanska

  • Vrbica – Mikanovačka and Kešinačka streets, but this month no works were carried out in the Vrbica settlement

  • Mrzović – Bojana Street, Crna Bara Street, Potok Street, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

MINI PRESENTATION of the project – “Project to improve the water utility infrastructure of the Semeljci agglomeration”

MINI PRESENTATION of the project – “Project to improve the water utility infrastructure of the Semeljci agglomeration”

RADIO REPORTAGE

TV REPORTAGE

  • GRUPA 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GRUPA 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the bidder community Izgradnja VVK d.o.o. and Sokol d.o.o. and their subcontractors

  • GRUPA 3 – Works on improving the water supply system of the wider Đakovica area are being carried out by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In the organization of Đakovočki vodovod d.o.o., an education week was held for elementary school children from April 11-13, 2022. year as part of the largest and most valuable project in the area of ​​the Semeljci Municipality, the EU project “Project to improve the water utility infrastructure of the Semeljci agglomeration” co-financed from the Cohesion Fund.

In the territory of the Municipality and agglomeration of Semeljci, a three-day education was conducted in 7 schools; Josip Kozarac primary school in Semeljci, and district schools Kešinci, Koritna, Mrzović, Vrbica, Forkuševci and Vučevci. About 100 children of primary school age were involved in the education project.

The education of schoolchildren was done in the form of a play/quiz in which, suitable for elementary school age, the goals of the project were discussed, the reduction of the direct discharge of untreated wastewater into surface waters by the construction of a wastewater treatment plant, the importance of preserving drinking water, the proper disposal and treatment of wastewater, etc. .

We must praise the knowledge of our little fellow citizens and conclude with pride that our water treasure will be in safe hands.

PRESS CONFERENCE/VISIT TO THE PROJECT CONSTRUCTION SITE – “Project to improve the water utility infrastructure of the Semeljci agglomeration”

PRESS CONFERENCE/VISIT TO THE PROJECT CONSTRUCTION SITE

“Project to improve the water utility infrastructure of the Semeljci agglomeration”

  • GRUPA 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GRUPA 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the bidder community Izgradnja VVK d.o.o. and Sokol d.o.o. and their subcontractors

  • GRUPA 3 – Works on improving the water supply system of the wider Đakovica area are being carried out by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

RADIO REPORTAGE 1

RADIO REPORTAGE 2

TV REPORTAGE 1

TV REPORTAGE 2

Organized by Đakovo waterworks d.o.o. and the Municipality of Semeljci on November 8, 2021. in Semeljci, a press conference was held and a visit to the construction site of the largest and most valuable project in the area of ​​this municipality, the EU project “Project to improve the water utility infrastructure of the Semeljci agglomeration” co-financed from the Cohesion Fund. In addition to the conference, a tour of the construction site in Vrbica in Mrzovička Street was also held.

The beneficiary of the project is Đakovočki vodovod d.o.o., and the total value is HRK 219,567,261.25; 69.3% are EU grants, and the rest are co-financed by the Ministry of Economy and Sustainable Development (13.30%), Hrvatske vode (13.30%), Semeljci Municipality (3.52%) and Đakovo water supply (0.57%) .

The press conference was attended by Mrs. Elizabeta Kos, Director of the Directorate of Water Management and Sea Protection, Mr. Zoran Đuroković, General Director of Croatian Waters, Mr. Josip Miletić, Deputy Prefect of Osječkobaranjska County, Mr. Antun Galić, Deputy Mayor of the City of Đakovo, Mr. Grga Lončarević, Head of Semeljci Municipality, and Mr. Ivan Kočiš, Director Đakovočko vodovodova d.o.o.

As part of the project, a pipeline will be built and reconstructed on the water supply and drainage system in the area of ​​the municipalities of Semeljci and Viškovci and the town of Đakovo (the settlements of Koritna, Kešinci, Semeljci and Mrzović and Vrbica). The construction of new pumping stations is planned, as well as the construction of a wastewater treatment plant (4,800 ES).

Director of Đakovo waterworks d.o.o. Mr. Ivan Kočiš addressed the crowd and at the same time presented the project through a presentation. He also added that this project is historic for the Municipality of Semeljci.

The mayor of the municipality, Mr. Grga Lončarević, agreed with the same and pointed out that this project is more valuable than the entire infrastructure built so far in the municipality of Semeljci, and invited all the residents to join the system.

How important the project is for the entire Osijek-Baranja County, the Deputy Prefect Mr. Josip Miletić emphasized and expressed satisfaction that this project, i.e. numerous new connections, line infrastructure, but also everything that is needed for better economic development, will significantly to improve the quality of life of the residents of Semeljac and the entire area covered by the Đakovo Waterworks. He pointed out that agglomerations worth HRK 2 billion are being implemented in the area of ​​Osijek-Baranja County.

The general director of Hrvatske vode, Mr. Zoran Đuroković, said that thanks to these types of projects, our country is getting closer to European standards for household drainage system coverage. – It is about more than 50 kilometers of sewage collectors, thanks to which more than 3,600 inhabitants will be connected to the public drainage system. Up until now, there was no drainage with wastewater treatment in the area of ​​Semeljci Municipality, and now more than 90% of public drainage will be solved.

Director of the Directorate of Water Management and Sea Protection of the Ministry of Economy and Sustainable Development, Mrs. Elizabeta Kos pointed out that the Semeljci agglomeration project is one of 60 projects approved in the 2014-2020 program period. whose total value is more than HRK 25 billion, of which more than HRK 20 billion are eligible costs. “The Ministry is a partner in this project, so in addition to participating in the implementation of the approval and preparation of the project, we also co-finance this project with about 13%. The municipality of Semeljci will get a connection to the public drainage and water supply systems, and I emphasize that the preparations for the connection are also acceptable costs from EU funds, so the citizens will also participate less in the costs.

PHOTOS

State of the project on 31.05.2022. year

State of the project on 31.05.2022. year

During the month of May, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

A total of 16,429.17 meters of drainage pipelines (32.01%) have been constructed so far, out of a total of 50,826.46 meters, and 12,197.80 meters of water supply pipelines (51.94%), out of a total of 23,482.87 meters planned.

Realization of works from 31.05.2022. years below

So far, the works have included the following streets:

  • Semeljci – Street Braće Radića, Street Tune Rakitića, Street Kralja Tomislava, Kolodvorska Street, Street Antuna Mihanovića i Street Vladimira Nazora

  • Koritna – Street Josipa Kozarca, Street Marka Mutaje

  • Kešinci – Street Ive Lole Ribara, Street Matije Gupca, Street Solara, Street Ljudevita Gaja, Street Braće Radić, Doljanska

  • Vrbica – nisu se izvodili radovi

  • Mrzović – Street Bojana, Street Crna Bara, Street Potok, Županijska cesta ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

State of the project on 30.04.2022. year

State of the project on 30.04.2022. year

During the month of April, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 9,502.25 meters of drainage pipelines (18.70%), out of a total of 50,826.46 meters, and 11,380.27 meters of water supply pipelines (48.46%), out of a total of 23,482.87 meters planned, have been constructed so far.

Realization of works from 30.04.2022. years below

So far, the works have included the following streets:

  • SemeljciBraće Radića Street, Kralja Tomislava Street, Kolodvorska Street, Antun Mihanovića Street and Vladimira Nazor Street    

  • KoritnaJosipa Kozarac Street, Marko Mutaja Street

  • KešinciIva Lola Ribara Street, Matije Gupca Street, Solara Street, Ljudevita Gaja Street, Braće Radić Street

  • Vrbicano works were carried out

  • MrzovićBojana Street, Crna Bara Street, Potok Street, County Road ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

State of the project on 31.03.2022. year

State of the project on 31.03.2022. year

During the month of March, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 9,502.25 meters of drainage pipelines (18.70%), out of a total of 50,826.46 meters, and 11,380.27 meters of water supply pipelines (48.46%), out of a total of 23,482.87 meters planned, have been constructed so far.

Realization of works from 30.11.2022. years below

So far, the works have included the following streets:

  • Semeljci – Kralja Tomislava Street and Tuna Rakitić

  • Street Koritna – Josip Kozarac Street and Marko Mutaja

  • Street Kešinci – Iva Lola Ribara Street and Braće Radić

  • Street Vrbica – no works were carried out Mrzović – Crna Bara Street and Bojana Street

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA