State of the project on 31.01.2024. year

During the month of February, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of February, preparatory and earthworks for the facility of mechanical pretreatment and biological treatment of waste water, construction of a piezometer, construction of the foundations of the Plant’s fences, and work on the Plant’s administrative building were carried out.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Picture of the construction site

  • Picture 2: Concreting of the fence

  • Picture 3: Administrative building – concreting of AB slab

  • Picture 4: Performance of the piezometer