State of the project on 30.04.2024. year

During the month of April, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

 

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of April, preparatory and earthworks for the mechanical facility were carried out pretreatment and biological treatment of waste water, works on the administrative building of the Plant and preparatory works on the fields for earthing of sludge, preparatory works on covered buildings parking for cars and covered parking for trucks and special vehicles.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

PICTURE GALLERY:

  • Picture 1: Picture of the construction site

  • Picture 2: Inlet pumping station of the mechanical pretreatment facility

  • Picture 3 and 4: Biological waste water treatment facility