State of the project on 30.11.2023. year

During the month of Decmber, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 50,771.37 meters of drainage pipelines (100%) and 23,440.67 meters of water supply pipelines (100%) have been constructed so far.

Realization of works from 30.11.2023. year below  

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

  • As part of the works on Group 1, 18,965.46 m of drainage pipelines and 11,242.87 m of water supply pipelines were constructed in the settlements of Semeljci, Kešinci and Koritna.

GROUP 2 – VRBICA SETTLEMENT

  • As part of the works on Group 2, 18,965.46 m of drainage pipelines were constructed in the settlements of Mrzović and Vrbica.

GROUP 3

  • As part of the works on Group 3 in the area of ​​the city of Đakovo, 12,197.80 m of water supply pipelines were constructed.

_________________________________________________________________________________________________

Construction of a wastewater treatment plant in the Semeljci agglomeration

As part of the Contract for the Construction of a Wastewater Treatment Plant in the Semeljci agglomeration, an access road will be built to the location of the Wastewater Treatment Plant and the Wastewater Treatment Plant.

On April 19, 2023. a construction permit was obtained for the access road to the location of the waste water treatment plant, and on 07.06.2023. the registration of the construction site was carried out.

On 17.10.2023. a building permit was obtained for the waste water treatment plant and on 17.11.2023. registration of the construction site has been completed.

During the month of November, preparatory and earthworks were carried out on the access road and preparatory and earthworks on the excavation for the facility of mechanical pretreatment and biological treatment of waste water.

The location of the future UPOV in Semeljka, c.no. no. 1159/3 k.o. Villagers

Pictures: Earthworks on the excavation of a construction pit for mechanical pretreatment and biological treatment of water

Pictures: Earthworks on the access road