PUBLIC PRESENTATION/VISIT TO THE CONSTRUCTION SITE of the project – “Project to improve the water utility infrastructure of the Semeljci agglomeration”

  • GRUPA 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GRUPA 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the bidder community Izgradnja VVK d.o.o. and Sokol d.o.o. and their subcontractors

  • GRUPA 3 – Works on improving the water supply system of the wider Đakovica area are being carried out by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

RADIO REPORTAGE 1:

RADIO REPORTAGE 2:

TV REPORTAGE 1

TV REPORTAGE 2

During the visit to the construction site on 5.12. In 2022, Project stakeholders, representatives of Đakovočko vodovod d.o.o., the Municipality of Semeljci and Hrvatske voda visited locations in Kolodvorska Street and Vladimira Nazor Street in Semeljci and visited informative stands where the Project was promoted by distributing promotional materials, all with the aim of informing and educating about the importance water utility infrastructure.

The visit to the construction site and the presentation were attended by Mr. Ivan Kočiš, director of Đakovo waterworks d.o.o., Mr. Tvrtko Juroš, representative of the contractor, Mr. Milan Matić, project manager, Mr. Grga Lončarević, head of the Municipality of Semeljci, Mr. Marin Mandarić, Member of Parliament and Mayor of the City of Đakovo, and a representative of the Croatian led by Mr. Željko Kovačević, director of VGO Osijek.

The mayor of the municipality, Mr. Grga Lončarević, pointed out that this project has a greater financial value than all the infrastructure built so far in the municipality of Semeljka. At the presentation itself, the Member of Parliament and Mayor of the City of Đakovo, Mr. Marin Mandarić, spoke and asked the citizens for patience during the execution of the works and congratulated all stakeholders that the Project is proceeding according to the planned dynamics. Finally, the representative of Hrvatske vode, the director of VGO Osijek, Mr. Željko Kovačević, spoke and expressed his satisfaction with the Project itself and especially praised all collaborators on the Semeljci agglomeration project.

OVERALL DRAINAGE AND WATER SUPPLY LINE BUILDINGS HAVE BEEN CARRIED OUT SO FAR:

  • 34,012.42 meters of drainage pipelines (67%), out of a total of 50,826.46 meters and

  • 16,379.80 meters of water supply pipelines (70%), out of a total of 23,482.87 meters planned.

VIEWED BY SETTLEMENT, THE CURRENT STATE OF WORK ON THE DRAINAGE SYSTEM IS AS FOLLOWS:

SEMELJCI – 10,736 meters of drainage pipeline out of 12,581 (85%) were constructed.

KORITNA – constructed 3,316 meters of drainage pipeline out of 11,138 (30 %).

KEŠINCI – 7,584 meters of drainage pipeline out of 8,140 (93%) were constructed.

VRBICA – constructed 3,207 meters of drainage pipeline out of 9,826 (33 %).

MRZOVIĆ – constructed 9,168 meters of drainage pipeline of 9,168 (100%)

FOTOGRAFIJE