State of the project on 31.03.2022. year

During the month of March, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.

  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 9,502.25 meters of drainage pipelines (18.70%), out of a total of 50,826.46 meters, and 11,380.27 meters of water supply pipelines (48.46%), out of a total of 23,482.87 meters planned, have been constructed so far.

Realization of works from 30.11.2022. years below

So far, the works have included the following streets:

  • Semeljci – Kralja Tomislava Street and Tuna Rakitić

  • Street Koritna – Josip Kozarac Street and Marko Mutaja

  • Street Kešinci – Iva Lola Ribara Street and Braće Radić

  • Street Vrbica – no works were carried out Mrzović – Crna Bara Street and Bojana Street

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA