During the month of February, the works that started at the end of 2021 continued.
- GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.
GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.
In total, 34,307.11 meters of drainage pipelines (67.50%) have been constructed so far, out of a total of 50,826.46 meters and 16,579.80 meters of water supply pipelines (70.60%), out of a total of 23,482.87 meters planned.