State of the project on 28.02.2023. year

During the month of February, the works that started at the end of 2021 continued.

  • GROUP 1 – Works on the construction of the waste water drainage system in the settlements of Koritna, Kešinci and Semeljci and works on the improvement of the water supply system in the area of ​​the municipality of Semeljci are performed by the tenderer community Sokol d.o.o. and Izgradnja VVK d.o.o., and their subcontractors.
  • GROUP 2 – Works on the construction of the waste water drainage system in the settlements of Mrzović and Vrbica are performed by the tenderer community Izgradnja VVK d.o.o. and Sokol d.o.o., and their subcontractors.

  • GROUP 3 – Works on the improvement of the water supply system of the wider Đakovica area are performed by a community of bidders: Sokol d.o.o., Izgradnja VVK d.o.o., Vodovod-Montaža d.o.o. and Crocus d.o.o.

In total, 34,307.11 meters of drainage pipelines (67.50%) have been constructed so far, out of a total of 50,826.46 meters and 16,579.80 meters of water supply pipelines (70.60%), out of a total of 23,482.87 meters planned.

Realization of works from 28.02.2023. year below

So far, the works have included the following streets:

  • Semeljci –  Street Braće Radića,  Street Tune Rakitića,  Street Kralja Tomislava, Kolodvorska  Street,  Street Antuna Mihanovića,  Street Vladimira Nazora, Školska  Street,  Street Augusta Šenoe, Street Ivana Kozarca                                                      
  • Koritna –  Street Josipa Kozarca,  Street Marka Mutaje,  Street Rade Končar, Strossmayer Street, Street Matije Gupca

  • Kešinci –  Street Ive Lole Ribara,  Street Matije Gupca,  Street Solara,  Street Ljudevita Gaja,  Street Braće Radić, Doljanska, Balkanska

  • Vrbica –  Street Kešinačka,  Street Mikanovačka, Street Đurđanačka, Street Mrzovička

  • Mrzović –  Street Vrbička,  Street Bojana,  Street Crna Bara,  Street Potok, ŽC 4132

GROUP 1 – SETTLEMENTS OF SEMELJCI, KEŠINCI AND KORITNA

GROUP 2 – MRZOVIĆ SETTLEMENT

GROUP 3 – WORKS ON THE IMPROVEMENT OF THE WATER SUPPLY SYSTEM IN THE EXTENT OF ĐAKOVAČ AREA

 

WASTE WATER TREATMENT PLANT – UPOV SEMELJCI

 

  • Currently, the design phase is in progress and all the necessary investigative and field work, including excavating, is underway all necessary permits and approvals.

 

A view of the location of the future UPOV Semeljci